Technical due diligence examines whether a data center can deliver the capacity promised to customers, within the planned budget and timetable. For investors and lenders, the review connects the power supply, electrical design, contracts and test evidence.
Power first
The review starts with the supply: the grid connection agreement, the operator’s works and their dates, backup generation, and any on-site solar and battery storage. If power is available only after the contracted service date, service delivery and revenue may be delayed. The financial model needs to reflect that risk. This part of the review is covered in our article on powering a data center.
Design against the claimed level
The design documents are read against the availability level in the customer contract, whether it is expressed as a Uptime Institute Tier, an EN 50600 class or a TIA-942 rating. The reviewer traces the electrical single-line diagram from the utility intake to the rack: transformers, medium and low voltage switchgear, uninterruptible power supplies, generators and distribution. The points of interest are redundancy at full design load, single points of failure and protection coordination.
Contracts, cost and schedule
- Construction contract: scope gaps between the contractor, the equipment suppliers and the owner; completion tests; delay and performance damages.
- Long-lead equipment: transformers, switchgear and generators often set the critical path. Purchase orders and factory slots are evidence; a programme line is not.
- Budget: cost per megawatt of IT load against comparable projects, and the contingency held.
- Permits: building, environmental and grid approvals, and the conditions attached.
Commissioning, in five levels
Data center commissioning is commonly organised in five levels, and an independent party can witness each:
- Factory witness testing of the main equipment.
- Delivery and installation checks on site.
- Pre-functional checks and start-up of each item.
- Functional performance tests of each system.
- Integrated systems testing (IST): the whole facility under load, with utility power cut and failures simulated.
The fifth level is the evidence a lender should ask for. It shows whether the systems work together as the design claims, under a load bank standing in for the customer’s equipment.
Operation
For an operating asset, the review adds the record: incidents and their root causes, maintenance carried out against the plan, measured power usage effectiveness (PUE, defined in ISO/IEC 30134-2) against the design value, and the capacity actually remaining for new customers.
During construction
After financial close the lender’s technical advisor reports at intervals: progress against the programme, certificates for drawdown, changes to the design, test results and the completion certificate. Independent reporting helps the lender understand what has been completed, what remains unresolved and how changes affect the project’s technical risks.