Before committing to a data center project, an investor needs to know how much power the site can receive and when it will be available. The grid connection plan should support each phase of the development and the capacity promised to customers.

The grid connection sets the timetable

A connection agreement states a capacity and a date. Both deserve a close reading:

  • Capacity: the contracted import capacity, in MVA or MW, and whether it is firm or can be curtailed by the system operator.
  • Schedule: the works the operator must complete before energisation, such as a new substation, a transformer or a line, and who pays for them.
  • Redundancy: whether the site is fed from one substation or two, and whether the feeders share a route.
  • Ramp: the load a data center draws in its first years is well below its final load. The connection should match the phases of the build, not only the last one.

If the connection date falls behind the planned opening, the revenue timetable needs to be reassessed.

What on-site solar can and cannot do

A data center draws an almost constant load, day and night. A solar plant produces during the day and its output changes with the season. On-site or nearby solar therefore lowers the energy bought from the grid and the carbon intensity of the supply, but it does not replace the connection.

The questions are the ones asked of any solar investment, with one addition:

  • Energy yield: the long-term production estimate, its uncertainty and the losses assumed.
  • Coverage: the share of the facility’s annual consumption the plant can supply, hour by hour, not as an annual average.
  • Land and connection: whether the plant sits behind the facility’s meter or feeds the grid elsewhere under a supply contract.

The role of battery storage

Battery energy storage systems (BESS) appear in a data center’s power plan in three roles, and each must be sized for its own duty:

  • Shifting solar energy from midday into the evening.
  • Limiting peak demand drawn from the grid.
  • Supporting backup power, alongside or in place of part of the generator fleet, for a defined duration.

A battery sized for one role is often credited with all three in the business case. The usable capacity, the degradation over the years and the operating strategy decide which of them it can deliver.

Backup generation and fuel

Generators remain the usual long-duration backup. Their rating, their number relative to the load (N, N+1, 2N), the fuel stored on site and the refuelling contract determine how long the facility can run without the grid. These figures should agree with the availability class the facility claims.

What an independent review covers

An independent technical review of the power supply plan compares the documents with each other and with the site:

  • The connection agreement, and the operator’s works programme, against the build phases.
  • The yield assessment of the solar plant against measured data and the assumed consumption profile.
  • The storage sizing and its degradation assumptions against the duties assigned to it.
  • The single-line diagram against the redundancy the design claims.

The review identifies which assumptions are supported by evidence and which still need to be resolved before an investment decision.