Ankara
Case study · Kalyon Enerji
On the first 200 MWac phase of the Karapınar YEKA project we contributed site checks and progress reporting within the lender's engineering.

Karapınar is Türkiye's largest solar power plant and one of the largest single-site solar plants in the world. A flagship of the YEKA programme, it is expected to meet the annual electricity needs of around 2 million people.
The Karapınar YEKA project, 1,350 MWp in total, was delivered in two parts of 200 MWac and 800 MWac.
We carried out general checks of the equipment arriving on site, followed the progress of construction and reported our observations.
Our work provided technical information on the condition of this phase on site.
Sources: Milliyet · Clifford Chance